Project Overview

CML / Rhenus required a full warehouse strip-out at their Magna Park Leicester facility after the site lease had ended.

Nexus were appointed to deliver a complete turnkey removal of all storage infrastructure, building services and fire systems—on a tight 10-week programme.

CML - Rhenus Magna Park - Leicester | Case Study | Nexus Storage Solutions

The Challenge:

  • Complete removal of all warehouse infrastructure before lease termination
  • Decommission a large multi-tier storage and picking environment
  • Manage the dismantling of high-level services including sprinklers
  • Deliver everything within a strict 10-week timeframe

Our Solution:

Nexus delivered a full turnkey strip-out including:

  • 100,000 sqft 3-tier mezzanine pick tower fully dismantled
  • Removal of 15,000 pallet locations of pallet racking
  • Safe decommissioning and removal of the in-rack fire sprinkler system
  • All works completed to landlord handover requirements
  • On-site project management of all trades, including safety, waste disposal and compliance
CML / Rhenus Magna Park Leicester | Strip Out | Nexus Storage Solutions

Delivery & Programme:

The entire strip-out was delivered in 10 weeks, with multiple teams working in parallel and careful sequencing to safely remove high-level structures and services.

Result:

The warehouse was returned to a clean, empty, landlord-ready condition ahead of the lease deadline.

Key Outcomes:

  • Full removal of 3-tier mezzanine and racking
  • Sprinkler system safely decommissioned
  • 100k sqft warehouse stripped and cleared
  • Delivered on time

What Nexus clients say….

Down-dir Down-dir

” Thank you for your fast turnaround and support during this installation.”

“ The installation looks better than we expected. The team did a great job and worked safely which is paramount to us and our operation. ”

” Everything was supplied and installed safely, efficiently and on-time. ”

” A great project to be involved with and the team delivered safely, ontime and to the highest standards, we can’t wait to start operating from the site. ”

” Nick and the team were great, from initial consultation to handover we were kept informed and the project was handed over early and within budget. ”

SafeContractor Approved | Nexus Storage Solutions
CQMS Safety Scheme Member | Nexus Storage Solutions
SSIP Member | Nexus Storage Solutions
CITB Member | Nexus Storage Solutions